  • 2 - Fingerprints - Project Milestone
    Apr 1, 2021–Sep 1, 2021
    Expired PhD project wasmer / Projects / single-impurity-database
    3 Issues · 0 Merge requests
    0% complete
  • 3 - Models - Project Milestone
    Jul 1, 2021–Oct 1, 2021
    Expired PhD project wasmer / Projects / single-impurity-database
    0 Issues · 0 Merge requests
    0% complete
  • 1 - Data generation - Project Milestone
    Jan 1, 2021–Oct 1, 2021
    Expired PhD project wasmer / Projects / single-impurity-database
    7 Issues · 0 Merge requests
    57% complete
  • 4 - Evaluation - Project Milestone
    Aug 1, 2021–Oct 10, 2021
    Expired PhD project wasmer / Projects / single-impurity-database
    0 Issues · 0 Merge requests
    0% complete
  • 5 - Writing - Project Milestone
    Jun 1, 2021–Oct 14, 2021
    Expired PhD project wasmer / Projects / single-impurity-database
    0 Issues · 0 Merge requests
    0% complete